Project Description

The new “Administrative Measures for Installation (Repair, Test) Power Facilities Permits” will come into effect on October 11, 2020. The “Administrative Measures for Installation (Repair, Test) Power Facilities License” (State Electricity Regulatory Commission Order No. 28) promulgated by the former State Electricity Regulatory Commission on December 18, 2009 shall be repealed at the same time. Litai Power briefly introduces the new version of the guide for the selection of construction machinery and equipment required for the first-level power facility license for installation (repair, test) testing.

This table describes laboratory standards such as high-voltage generating equipment, electrical measuring instruments, oil and gas testing instruments, and commonly used instrument tables.

First-level installation (repair, test) power facility license test equipment and laboratory standard test category
Serial numberMachine and equipment nameUnitQuantityRegulationsProduct model
OneHigh-voltage generating equipment
1DC high voltage generatorset1DC:400kV/3mAZGF-400KV/3mA 
set1DC:250kV/5mA ZGF-250KV/5mA
set1DC:120kV/2mAZGF-120KV/2mA 
2Power frequency AC withstand voltage test complete setset1AC:20kVA/180kVLTYD-20KVA/180KV 
set1AC:20kVA/100kVLTYD-20/100 
set1AC:15kVA/60kVLTYD-15/60 
3Frequency conversion series resonance test complete setset14000kVA/800kV×1/200kV*2/5A         30~300HzLTZB-4000KVA/800KV 
4Transformer partial discharge detection complete setset1400kW以上   30~300HzLTJF-400KW 
Two Electrical measuring instruments
1High voltage dielectric loss testerstation2Anti-interference frequency conversionLTGS-II 
2Loop resistance testerstation2DC: ≥100A LTHL
3Transformer volt-ampere characteristic testerstation12200V/1A LTFA-B
station11100V/5ALTFA-F 
4Large grounding grid grounding resistance testerstation15A >30A
station1Frequency conversion LTDW 
5Capacitance and inductance testerstation1Three simultaneous measurementsLTDR 
6Ground continuity testerstation1DC: 10A LTDT
7Transformer DC Resistance Testerstation2DC: ≥10ALTZR-10A 
8Transformer ratio testerstation1DigitalLTBC-II 
9Transformer winding deformation testerstation1Impedance method, frequency response methodLTRZ-B 
10Transformer on-load tap changer characteristic testerstation1I≥1ALTKC 
11Circuit breaker characteristic testerstation2 LT-3000
12Zinc oxide arrester resistive current testerstation1 LTBL
13Comprehensive relay protection testerstation2LTJB-1800 
14Transmission line parameter testerstation1LTXL 
15Large current generatorstation1 LTSLQ
16Lightning counter action testeronly1 LT-600
17Insulation Resistance Testerstation2 LT2550
18Cable fault testerset1 LTDL-V
19Cable identification instrumentset1 LTDS
20Transmitter calibratorset2
21Automatic tester for gas relay and pressure release valveset1
ThreeOil and gas test equipment
1SF6 leak detectorstation1XP-1 
2SF6 dew point meterstation1 LTDP00
3SF6 gas density relay calibratorstation1LTMD 
4SF6 gas composition comprehensive detectorstation1LTKS SF6 
5Chromatographstation1LTSP 
6Closed flash point meterstation1LTBS 
7Micro water meterstation1LTWS 
8Acid value testerstation1
9PH meterstation1
10Insulating oil dielectric loss testerstation1LTJJ 
11Insulating oil dielectric strength testerstation1 LTYJ
12Freezing point testerstation1
13conductivity meterstation1
14Surface Tension Testerstation1
FourCommonly used instruments
1Megohmmeterone30DC: 500V and aboveLT2550 
2Digital double clamp phase voltammeterone10Measuring current is less than 50mALTSMG 
3Phase sequence tableone10VC850 
4Clamp ammeterstation10500A
5Current transformer secondary circuit load testerstation320V/5A
6Three-phase voltage regulatorstation1015kVA